JURUPA VALLEY, Calif. — November 17, 2026. The cost and schedule for pedestrian and bicycle improvements along Pacific Avenue were the subject of a proposed contract change in the November 5 City Council packet.
Public Works staff requested Change Order No. 2 for Phase 2 of the project, a $312,784.81 increase that would take the construction contract with MDB General Engineering, Inc. from $2,018,917.26 to $2,331,702.07. The recommendation would also extend the contractor's time by 29 working days.
What the project includes
According to the city's staff report, Phase 2 runs from 42nd Street to Limonite Avenue. The work includes new curbs, gutters and sidewalks, pavement rehabilitation, drainage improvements, and signs and pavement markings intended to establish a bicycle route. The second phase builds on a previously completed first phase and is designed to finish corridor improvements between Sierra Avenue and Limonite Avenue.
What a change order does — and does not — show
Change orders can affect costs and construction time. The proposed $312,784.81 increase is not the entire project budget, and a proposed 29-day extension should not be mistaken for a fixed new opening date. The detailed cause, approved scope and schedule should be assessed against the staff report, change order and any final council approval.
This story documents the November 5 recommendation. It does not claim the City Council adopted it or that traffic restrictions are in force today. Residents should follow updated Public Works advisories for closures and detours.
Sources: official November 5 council agenda, item G; city Public Works staff report for Pacific Avenue Phase 2. Reviewed November 17, 2026.
Support Jurupa Valley News
Choose how to support Jurupa Valley News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Jurupa Valley News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Jurupa Valley News
- Jurupa Valley Reviews Three Income-Restricted Homes in Canterra Development Agreement →
- Jurupa Valley Officials Asked to Consider Moratorium or Ban on Data Centers →
- Jurupa Valley Proposes $366,168 Share for Country Village Road Paving During Pipeline Work →
- Jurupa Valley Proposes $5.7 Million Granite Hill Safe Routes to School Sidewalk Project →
- Jurupa Valley Weighs $5.7 Million Street Repaving Contract Across 31 Road Segments →
COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.